Project Description

Natural Period Monitoring

The scope of work consisted of developing a methodology for extending the lives and optimizing structural surveys of fixed oil platforms. Our model calibration method used natural period data obtained from field monitoring and resulted in a 30% overall decrease in the number of joints that need to be inspected.

Client: Genesis Energies
Final client: Petrobras

Monitoring Results
Equipment Installation
Model Calibration
Original Model Natural Periods (s) Messured Natural Periods (s) Calibrated Model Natural Periods (s)
First Mode 3,317 3.03 3.04
Second Mode 3,074 2.63 2.81
Third Mode 2,147 2.04 1.96
Original Model Natural Periods (s) Calibrated Model Natural Periods (s)
First Mode 3,317 3.04
Number of joints with fatigue life below 100 years 3,074 2.81
30% overall decrease in the number of joints that need to be inspected.